Blog
Blogs

Why EV Charger Deals Never Show Up in Purchase Orders

Andrew Boston
August 10, 2026

8 min read

How the three largest charging programs in the country move money without ever creating the document most vendors search for.

Start with a simple experiment: search government purchase orders for "charging station" and "charger," and read what comes back.

We did. We audited 38 matched purchase orders across 20 states. The single most expensive hit was a $24,395 locking cabinet that charges student cell phones. The rest were two-way radio chargers, power-tool batteries, and USB kiosks.

Zero were EV charging equipment. Not a low number. Zero.

The obvious conclusion is that the keyword is noisy. However, the more useful conclusion is structural. The three largest EV charging programs in the country carry roughly $12.5 billion in authorized federal funding, and none of them buys a charger the way a purchase-order feed expects. In most of this market, the purchase order a vendor is searching for never exists at all.

We followed each program through the federal record to see where the money becomes visible instead.

Finding 1

The government that funds the charger never buys it

The National Electric Vehicle Infrastructure program, known as NEVI, is the largest source of public charging money in the country: $5 billion in formula funds apportioned to states from 2022 through 2026 to build fast charging along designated highway corridors.

Here is what NEVI does not do: it does not have a state buy a single charger.

Instead, state DOTs open funding rounds and private entities apply as site hosts: fuel retailers, property owners, charging networks. The federal share covers up to 80 percent of eligible costs, and the applicant covers the rest. The state reimburses a private buildout. It never issues a purchase order, because it never takes ownership of the equipment.

That structure explains why the program's paper trail looks nothing like procurement. The searchable artifacts are the state deployment plan, the DOT solicitation for site hosts, and the conditional award. Each names a funded location and a responsible agency. None contains a purchase amount.

The program has also moved slowly enough that most of the market is still in that pre-construction paper stage. As of mid-2025, only 148 NEVI chargers were operational across 12 states, against billions apportioned.

Figure 1 · Where $12.5B of charging money actually goes
NEVI
$5B formula funds
Money goes to
State DOTs, then private site hosts: fuel retailers, property owners, charging networks
The charger arrives as
A reimbursed private buildout. The state never owns the equipment
What a PO feed sees
Nothing
CFI
$2.5B discretionary grants
Money goes to
Cities, counties, tribes, transit agencies, and planning organizations
The charger arrives as
A grant-funded local project, solicited by the grantee months or years later
What a PO feed sees
Nothing until the late-stage local RFP
Clean School Bus
$5B rebates + grants
Money goes to
School districts, with charging folded into the per-bus award amount
The charger arrives as
A line inside the bus deal, a co-op rider, a service agreement, or utility capital
What a PO feed sees
Rarely: a small electrical job
Sources: FHWA NEVI and CFI program records; EPA Clean School Bus Program

Finding 2

The grant award is the lead list

The Charging and Fueling Infrastructure program, or CFI, is a $2.5 billion discretionary program, and it is the one that actually funds SLED buyers: cities, counties, tribes, transit agencies, and planning organizations. FHWA publishes the recipient lists for every round on its program page.

Those lists matter because of what happens next. A CFI grantee does not receive chargers. It receives money and an obligation to run its own local procurement, months or years later.

The Michiana Area Council of Governments in northern Indiana shows the full sequence in one place. MACOG received a $4.2 million CFI award to deploy charging across four counties. The council then held two public pre-RFP meetings in August 2024, issued an RFP for Level 3 charging projects, and released two addenda that September, one after a site visit and one after the pre-submission meeting.

Read that timeline from a vendor's chair. The buyer, the budget, and the intent to solicit were public months before the RFP existed. A vendor watching the FHWA award list had most of a year to build a relationship. A vendor watching a bid feed got a compressed window and a field of competitors who had been there since the award.

Figure 2 · One CFI grant, start to solicitation · Michiana Area Council of Governments, IN
Early 2024
CFI award announced
$4.2M to MACOG to deploy EV charging across four counties. Buyer and budget are now public.
Aug 7 & 30, 2024
Public pre-RFP meetings
Two open meetings, slides posted, attendee questions on the record.
Sept 2024
Level 3 charging RFP
Solicitation live; two addenda follow a site visit and a pre-submission meeting.
Only now
The bid feed sees it
Vendors arriving here get a compressed window and a crowded field.
The vendor window: months of public notice before the solicitation existed
Source: MACOG CFI program page, engage.macog.com

Finding 3

The school-bus charger hides inside the bus deal

The third program is the largest single source of school-sector charging money in history, and it is the hardest to see.

EPA's Clean School Bus Program has awarded nearly $3 billion across one grant round and two rebate rounds, funding close to 8,500 bus replacements, most of them electric. Previous rounds provided up to $375,000 per electric bus, with charging infrastructure included in that figure. The charger money is real. It is simply folded into the price of the bus.

That bundling shapes how districts buy. In the program guidance and records we reviewed, the charger reaches the district through one of four paths, none of them a standalone charger purchase:

  1. Bundled with the bus. The dealer or manufacturer packages chargers into the bus order. The public record shows a bus purchase.
  2. A cooperative contract. Providers hold pre-competed Sourcewell contracts under an EV equipment and infrastructure category, so the district signs a rider instead of running a bid.
  3. A turnkey electrification partner. A service company owns and operates the buses and chargers under a multiyear agreement. The record shows a services contract.
  4. The utility builds it. Under make-ready and pay-as-you-save models, the utility covers the infrastructure, including charging equipment, and recovers costs on the electric bill. The record sits in a utility filing, not a district PO.

We saw this same shape in our license-plate-camera research, where East Ridge, Tennessee's only bid-feed artifact was the electrical work, not the cameras. School-bus charging repeats it at scale: if anything reaches a solicitation portal, it is often a modest electrical or site-work job. The wiring is visible. The chargers are not.

Figure 3 · Four ways a charger reaches a school district
Bundled with the bus

The dealer or manufacturer packages chargers into the electric bus order. Charging money sits inside the per-bus award amount.

Bid feed seesA bus purchase, no charger
Cooperative contract

The district signs onto a pre-competed contract, such as Sourcewell's EV equipment and infrastructure category, instead of running its own bid.

Bid feed seesNo local solicitation
Turnkey electrification partner

A fleet-services company owns and operates the buses and chargers under a multiyear agreement with one monthly cost.

Bid feed seesA services contract
The utility builds it

Make-ready and pay-as-you-save programs put the infrastructure, including charging equipment, on the utility's side of the ledger.

Bid feed seesA utility filing, not a district PO
If anything reaches a solicitation portal, it is often a modest electrical or site-work job. The wiring is visible. The chargers are not.
Sources: EPA Clean School Bus Program; DOE Alternative Fuels Data Center; Electrification Coalition

Finding 4

In 2026, the signal can die before the deal does

Every prior report in this series has argued that the earliest records are the most valuable. This category adds a harder lesson: an early record can also stop being true.

On January 20, 2025, Executive Order 14154 directed an immediate pause of grant disbursements for both NEVI and CFI. In February 2025, FHWA rescinded the NEVI guidance and suspended every approved state plan, writing that "effective immediately, no new obligations may occur under the NEVI Formula Program." The Government Accountability Office later found the withholding violated the Impoundment Control Act, and 16 states and the District of Columbia sued.

Then the paths split. FHWA issued revised guidance in August 2025 and ended the NEVI pause; FHWA apportioned $885 million for FY2026, and roughly ten states had opened or reopened funding rounds by early 2026. CFI went the other way: the program remained paused, a selection of existing awards was cancelled, and Congress transferred some unobligated NEVI funds to other purposes in the FY2026 appropriations act.

The school-bus program reset hardest of all. In February 2026, EPA cancelled the entire 2024 rebate round without making awards and announced a revamp in a release stating the prior administration "disastrously gave out around $2.7 billion", 90 percent of it for electric buses. The request for information that will shape the 2026 funding round closed in April, and a new opportunity is expected later this year.

For a seller, both halves are signals. A grantee whose CFI award was cancelled has no money to spend. A district that applied to the cancelled rebate round has documented demand and no funding, and that second group is the interesting one: more than 1,200 districts have been through this program once, and the cancelled round's applicants now form a public roster of school systems waiting on a notice of funding opportunity.

Figure 4 · Where the money stood, mid-2026
NEVI
Restarted

Paused February 2025, rebooted under revised guidance in August 2025. $885M apportioned for FY2026, with roughly ten states opening or reopening funding rounds. Some unobligated funds were transferred to other programs in the FY2026 appropriations act.

Watch: new state host solicitations, and community-site rounds in states that finished their corridors.

CFI
Verify awards

Disbursements paused under Executive Order 14154; a selection of existing awards was later cancelled. A grantee on a published award list may no longer hold funded demand.

Watch: award status before outreach. Grantees with intact funding still owe a local procurement.

Clean School Bus
Resetting

The 2024 rebate round was cancelled in February 2026 with no awards made. A revamped 2026 funding opportunity is expected, with broader fuel options. More than 1,200 districts have been through the program once already.

Watch: the 2026 NOFO. Applicants to the cancelled round are a public roster of districts with documented demand and no funding.

A 2024 award list is not a 2026 pipeline. Verify the money before you prospect the buyer.
Sources: Congressional Research Service R48996; FHWA; EPA, February 2026

Where the pattern breaks

  1. Charger-named solicitations do exist downstream of the grants. MACOG's Level 3 RFP is exactly that. The point is not that the RFP never comes; it is that the award named the buyer months earlier, and the RFP is the last public step rather than the first.
  2. Some districts do run open procurements. World Resources Institute's procurement guidance notes that "many will put the school bus and charger purchase out to bid" to evaluate vendors and new business models, especially for larger deployments. Those solicitations are usually titled around buses, not chargers.
  3. NEVI's own rules are widening the map. States that finish their highway corridors can now spend NEVI funds at community locations on any public road, which pushes future rounds toward exactly the local, publicly owned sites where conventional procurement is more likely.
  4. Our own starting number carries a caveat. The 38 audited purchase orders came from keyword sweeps, and keyword matching finds whatever shares the word. Genuine EV purchases filed under other terms would not surface in those cuts, which is the finding, not a flaw in it.

The verdict

We began with a search that found nothing, and the temptation was to treat the zero as a data problem.

It is not. The zero is an accurate description of how this market works. NEVI reimburses private site hosts, so no government purchase order exists. CFI funds local governments that solicit later, so the purchase order is the last artifact, not the first. The Clean School Bus Program folds the charger into the bus, the cooperative rider, the service agreement, or the utility's capital plan, so the purchase order is usually someone else's document entirely.

The market is large, funded, and visible. It is just visible in apportionment tables, state deployment plans, award lists, board acceptance votes, and pre-RFP meeting notices. A vendor who waits for the words "charging station" to appear in a purchase-order feed is not late to this market. In most of it, that vendor is waiting for a document that will never arrive.

See the deal before it becomes a bid. Tell us what you sell, and we will show you where demand is forming in your market, in budgets, council actions, and grant awards, before a solicitation is posted. Book a demo.

Methodology: program-level figures in this report come from federal primary sources, including FHWA, EPA, the Federal Register, GAO, and Congressional Research Service summaries, each linked where cited. The purchase-order audit draws on NationGraph's index of public records; 38 keyword-matched purchase orders were individually audited and classified on visible line-item text.

#evcharging #evchargers #nevi #cleanschoolbus #cfi #publicsector #governmentprocurement #buyingsignals #preRFP #nationgraph
Andrew Boston
Growth Associate

Find your first opportunity in minutes